COVER

Table of Content

EXECUTIVE SUMMARY

1.             INTRODUCTION.. 1

1.1       Background  1

1.2       Project Organisation  1

1.3       Construction Works undertaken during the Reporting Month  1

1.4       Summary of EM&A Requirements  7

2.             AIR QUALITY.. 10

2.1       Monitoring Requirements  10

2.2       Monitoring Locations  10

2.3       Monitoring Equipment 11

2.4       Monitoring Parameters, Frequency and Duration  12

2.5       Monitoring Procedures and Calibration Details  12

2.6       Results and Observations  13

3.             NOISE.. 14

3.1       Monitoring Requirements  14

3.2       Monitoring Locations  14

3.3       Monitoring Equipment 15

3.4       Monitoring Parameters, Frequency and Duration  15

3.5       Monitoring Procedures and Calibration Details  15

3.6       Results and Observations  16

4.             ENVIRONMENTAL AUDIT.. 19

4.1       Review of Environmental Monitoring Procedures  19

4.2       Assessment of Environmental Monitoring Results  19

4.3       Site Environmental Audit 20

4.4       Status of Environmental Licensing and Permitting  20

4.5       Implementation Status of Environmental Mitigation Measures  23

4.6       Implementation Status of Event/Action Plans  23

4.7       Implementation Status of Environmental Complaint Handling Procedures  23

5.             FUTURE KEY ISSUES. 25

5.1       Status of Natural Gas supply  25

5.2       Key Issues for the Coming Month  25

5.3       Monitoring Schedules for the Next 3 Months  26

5.4       Construction Program for the Next 3 Months  27

6.             CONCLUSION.. 28

 


List of Tables

 

Table 1.1          Construction Activities and Their Corresponding Environmental Mitigation Measures

Table 2.1          Air Quality Monitoring Locations

Table 2.2          Air Quality Monitoring Equipment

Table 2.3          Air Quality Monitoring Parameter, Duration and Frequency

Table 3.1          Noise Monitoring Locations

Table 3.2          Noise Monitoring Equipment

Table 3.3          Noise Monitoring Duration and Parameter

Table 4.1          Summary of AL Level Exceedances on Monitoring Parameters

Table 4.2          Estimated Amounts of Waste Generated in May 2005

Table 4.3          Summary of Environmental Licensing and Permit Status

Table 4.4          Environmental Complaints / Enquiries Received in May 2005

Table 4.5          Outstanding Environmental Complaints / Enquiries Carried Over

 

 

List of figures

 

Figure 1.1         Layout of Work Site

Figure 1.2         Cable Route of Transmission System

Figure 1.3         Location of Dumping Area

Figure 2.1         Location of Air Quality Monitoring Stations

Figure 3.1         Location of Noise Monitoring Stations

Figure 3.2         Location of Manual Noise Monitoring

 

 

Appendices

 

Appendix A      Organization Chart

Appendix B      Action and Limit Levels for Air Quality and Noise

Appendix C      Environmental Monitoring Schedule

Appendix D      Air Quality Monitoring Results for May 2005

Appendix E      Noise Monitoring Results for May 2005

Appendix F      The QA/QC Procedures and Results

Appendix G      Event/Action Plans

Appendix H      Site Audit Summary

Appendix I       Summary of EMIS

Appendix J       Tentative Construction Programme

Appendix K     Supply and Installation of Submarine Gas Pipeline – Monthly EM&A Report for May 2005 prepared by the Consultant as one of the ET Members

 

 

                                                                                                         

 



EXECUTIVE SUMMARY

 

This is the fiftieth monthly Environmental Monitoring and Audit (EM&A) report for the Project “Construction of Lamma Power Station Extension” prepared by the Environmental Team (ET).  This report presents the results of impact monitoring on air quality and noise for the said project in May 2005.

 

After successful completion of post-project monitoring in September 2002, no further marine water quality monitoring for the reclamation works would be required.

 

Air and noise monitoring were performed. The results were checked against the established Action/Limit (AL) levels.  An on-site audit was conducted once per week. The implementation status of the environmental mitigation measures, Event/Action Plan and environmental complaint handling procedures were also checked.

 

Construction Activities Undertaken

 

Construction activities for Lamma Extension during the reporting month are tabulated as follows:

 

Item

Construction Activities

Unit L9 Civil and Build Works

Main Station Building, 275kV Switching Station, Shunt Reactor, Chimney, Drainage, Fire Services Water Tank and Fire Pump House, C.W. Culvert System, C.W. Equipment Room, and Lamma Power Station Addition and Alteration (LPS A&A) Works

Unit L9 Mechanical Erection

HRSG Erection, Steam Turbine Erection, Gas Turbine Erection, Generator Erection, Condenser Erection, Aux Equipment Erection, Air duct / Inlet Filter, HRSG Inlet Duct, Piping Support / Piping Erection and insulation work

Unit L9 Electrical, Instrumentation & Control Erection

6.6 kV & 415V Switchgear, 415V Motor Control Centre (MCC), 380V Distribution Board (D/B), Auxiliary Transformer (Aux Tx), Charger & UPS and Cable Tray Installation

275kV Switching Station Erection

Materials Delivery & Installation of GIS and Shunt Reactors

Transmission System

Site formation work and tunnel excavation at the Lamma Power Station Cable Duct No.1, cable landing points N2, N4 & N5, filling of quarry spall, Type 2 and Type 1 rockfill at I1, N2, N4 & N5 respectively

Gas Pipeline

Pipe laying and trenching

Miscellaneous

Slurry ash piping & filling

 


Environmental Monitoring Works

 

One (1) air quality environmental monitoring work was rescheduled as shown in the following table.

 

Monitoring work

Original Schedule

Makeup sampling

Reasons

24 hour TSP monitoring at AM1

25/05/2005

27/05/2005

Failure of TSP Sampler

 

Other than this, all monitoring work at designated stations was performed as scheduled satisfactorily.

 

Air Quality

 

No exceedance of Action/Limit levels on 1-hour TSP and 24-hour TSP for air quality was recorded in the month.

 

Noise

 

Construction work for Lamma Extension was carried out during the restricted hours including evening-time, holidays and night-time under valid Construction Noise Permits.  No exceedance of Action and Limit levels for noise arising from the construction of Lamma Extension and transmission system was recorded in the month. 

 

Site Environmental Audit

 

Independent Environmental Checker (IEC) conducted a site inspection on 18/05/2005.  The inspection result is attached in Appendix H.

 

Site audits were carried out on a weekly basis to monitor environmental issues on the construction site.  The site conditions were generally satisfactory.  All required mitigation measures were implemented.

 

As the dredging work for formation of underwater trenches for transmission system has partially been completed on 11/8/2004 and will be suspended until June 2005, there will be no site audit for the underwater trenches work during this period.

 

Environmental Licensing and Permitting

 

Description

Permit No.

Valid Period

Issued To

Date of Issuance

From

To

Varied Environmental Permit

EP-071/2000/B

13/07/01

-

HEC

13/07/01

Varied Environmental Permit

EP-071/2000/C

18/05/05

-

HEC

18/05/05

Construction Noise Permit

GW-RS0668-04

06/01/05

02/07/05

Contractor

06/01/05

Construction Noise Permit

GW-RS0669-04

06/01/05

02/07/05

Contractor

06/01/05

Construction Noise Permit

GW-RS0678-04

10/01/05

09/07/05

Contractor

07/01/05

Construction Noise Permit

GW-RS0679-04

10/01/05

09/07/05

Contractor

06/01/05

Construction Noise Permit

GW-RS0084-05

16/02/05

02/08/05

Contractor

16/02/05

Construction Noise Permit

GW-RS0097-05

21/02/05

09/08/05

Contractor

18/02/05

Construction Noise Permit

GW-RE0018-05

25/02/05

24/08/05

Contractor

07/02/05

Construction Noise Permit

GW-RS0013-05

25/02/05

24/08/05

Contractor

21/02/05

Construction Noise Permit

GW-RN0062-05

02/03/05

01/09/05

Contractor

01/03/05

Construction Noise Permit

GW-RS0139-05

17/03/05

16/09/05

Contractor

17/03/05

Construction Noise Permit

GW-RS0146-05

21/03/05

20/09/05

Contractor

21/03/05

Construction Noise Permit

GW-RS0246-05

29/04/05

09/10/05

Contractor

29/04/05

Dumping Permit

EP/MD/05-115

01/03/05

31/08/05

Contractor

22/02/05

Dumping Permit

EP/MD/05-132

04/03/05

03/07/05

Contractor

03/03/05

Dumping Permit

EP/MD/06-002

09/05/05

08/06/05

Contractor

22/04/05

Registration of Chemical Waste Producer

WPN5213-912-P2781-07

11/06/04

-

Contractor

11/06/04

Registration of Chemical Waste Producer

WPN5213-912-K2801-03

15/09/04

-

Contractor

15/09/04

Registration of Chemical Waste Producer

WPN5517-912-T2007-01

08/12/92

-

Contractor

08/12/92

Registration of Chemical Waste Producer

WPN5213-912-W2852-09

25/01/05

-

Contractor

25/01/05

WPCO Discharge Licence

EP890/W2/XD020

22/11/04

30/11/09

Contractor

22/11/04

 

Implementation Status of Environmental Mitigation Measures

Environmental mitigation measures for the construction activities as recommended in the EM&A manual were implemented in the reporting month.

 

Environmental Complaints

One enquiry on the noise generated by the construction activities was received in the reporting month and it was shortly settled.  There was no non-compliance with the relevant requirements.

 

Future Key Issues

The future key issues to be considered in the coming month are as follows:

 

Unit L9 Civil and Building Works

 

-         to continue monitoring the noise level during construction and to ensure compliance with the CNP’s already obtained;

-         to continue executing the preventive measures for avoiding noise exceedance and keep monitoring/ reviewing the performance;

-         to monitor and review the sufficiency of the dust suppression measures provided and increase the resources accordingly if necessary;

 

Unit L9 Mechanical Erection

 

-         to continue monitoring the noise level during construction

-         to continue executing the preventive measures for avoiding noise exceedance and keep monitoring/ reviewing the performance;

-         to monitor and review the sufficiency of the dust suppression measures provided and increase the resources accordingly if necessary;

 

Unit L9 Electrical Erection

 

-         to continue monitoring the noise level during construction

-         to continue executing the preventive measures for avoiding noise exceedance and keep monitoring/ reviewing the performance;

-         to monitor and review the sufficiency of the dust suppression measures provided and increase the resources accordingly if necessary;

 

275KV Switching Station Erection

 

-         to continue monitoring the noise level during construction

-         to continue executing the preventive measures for avoiding noise exceedance and keep monitoring/ reviewing the performance;

-         to monitor and review the sufficiency of the dust suppression measures provided and increase the resources accordingly if necessary;

 

Transmission System

 

-         to continue monitoring the noise level during construction;

-         to continue executing the preventive measures for avoiding noise exceedance and keep monitoring/ reviewing the performance;

-         to monitor and review the sufficiency of the dust suppression measures provided and increase the resources accordingly if necessary;

-         to closely monitor the construction activities in order to avoid disturbance to the rare plants; 

-         to provide temporary fire fighting equipment for prevention of fire within the work sites.

 

Concluding Remarks

The environmental performance of the project was generally satisfactory.




1.             INTRODUCTION

 

1.1         Background

 

The Environmental Team (hereinafter called the “ET”) was formed within the Hongkong Electric Co. Ltd (HEC) to undertake Environmental Monitoring and Audit for Construction of Lamma Power Station Extension” (hereinafter called the “Project”).  Under the requirements of Section 6 of Environmental Permit EP-071/2000/B, an EM&A programme for impact environmental monitoring set out in the EM&A Manual (Construction Phase) is required to be implemented.  In accordance with the EM&A Manual, environmental monitoring of air quality, noise and water quality and regular environmental audits are required for the Project. As the post-project marine water monitoring was successfully completed in September 2002, no further water quality monitoring for the reclamation works would be required.

 

The Project involves the construction of a gas-fired power station employing combined cycled gas turbine technology, forming an extension to the existing Lamma Power Station.  The key elements of the Project including the construction activities associated with the transmission system and submarine gas pipeline are outlined as follows.

 

·          dredging and reclamation to form approximately 22 hectares of usable area;

·          construction of six 300MW class gas-fired combined cycle units;

·          construction of a gas receiving station;

·          construction of a new transmission system linking the Lamma Extension to load centres on Hong Kong Island;

·          laying of a gas pipeline for the supply of natural gas to the new power station

 

This report summarizes the environmental monitoring and audit work for the Project for the month of May 2005.

 

 

1.2         Project Organisation

 

An Environmental Management Committee (EMC) has been set up in HEC to oversee the Project.  The management structure includes the following:

 

·          Environmental Protection Department (The Authority);

·          Environmental Manager (The Chairman of the Environmental Management Committee);

·          Engineer;

·          Independent Environmental Checker (IEC);

·          Environmental Team (ET);

·          Contractor.

 

The project organisation chart for the construction EM&A programme is shown in Appendix A.

 

 

1.3         Construction Works undertaken during the Reporting Month

 

Construction activities for Unit L9 civil and building works were the for Main Station Building, 275kV Switching Station, Shunt Reactor, Chimney, Drainage, Fire Services Water Tank and Fire Pump House, C.W. Culvert System, C.W. Equipment Room and LPS A&A Works. Construction activities for Unit L9 mechanical works were the erection of HRSG, Steam Turbine, Gas Turbine Erection, Generator, Condenser, Auxiliary Equipment, Air duct / Inlet Filter, HRSG Inlet Duct, Piping Support / Piping and insulation work.  Construction activities for Unit L9 electrical, instrumentation & control erection were 6.6 kV & 415V Switchgear, 415V MCC, 380V D/B, Aux Tx, Charger & UPS and Cable Tray installation.  The construction activities for 275KV Switching Station erection were materials delivery & installation of GIS and Shunt Reactors.  Construction activities for Unit L9’s associated transmission system were site formation work and tunnel excavation at the Lamma Power Station Cable Duct No.1, cable landing points N2, N4 & N5, and filling of quarry spall, Type 2 and Type 1 rockfill at I1, N2, N4 & N5 respectively.  The underwater trenches work has partially been completed on 11/8/2004 and will be suspended until June 2005.  A separate monthly EM&A report for submarine pipeline prepared by the consultant, as one of ET members, is shown in Appendix K.  Uncontaminated materials were dumped at the assigned location within the South Cheung Chau Spoil Disposal Area.  Layout plans for construction site and transmission system are shown in Figure 1.1 and Figure 1.2 respectively.  Figure 1.3 shows the dumping location in May 2005.

 

The main construction activities carried out during the reporting month and the corresponding environmental mitigation measures are summarized in Table 1.1.  The implementation of major mitigation measures in the month is provided in Appendix I.

 

Table 1.1    Construction Activities and Their Corresponding Environmental Mitigation Measures

 

Item

Construction Activities

Environmental Mitigation Measures

Unit L9 Civil and Building Works

1

Main Station Building

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

2

275kV Switching Station

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

3

Shunt Reactor

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

4

Chimney

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

5

Drainage Works

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

6

Fire Services Water Tank and Fire Pump House

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

7

C.W. Culvert System

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

8

C.W. Equipment Room

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

9

LPS A&A Works

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

Construction of Transmission System

10

Site formation work and tunnel excavation at the Lamma Power Station Cable Duct No.1, cable landing points N2, N4 & N5

Air Quality

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Terrestrial Ecology

-                   Special care and close monitoring to avoid disturbances to the rare plant species.

-                   Temporary fire fighting equipment provided within the work area during construction.

11

Filling of quarry spall, Type 2 and Type 1 rockfill at I1, N2, N4 and N5 respectively

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

Unit L9 Mechanical Erection

12

HRSG Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

13

Steam Turbine Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

14

Gas Turbine Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

15

Generator Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

16

Condenser Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

17

Auxiliary Equipment Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

18

Air duct / Inlet Filter

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

19

HRSG Inlet Duct

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

20

Piping Support / Piping Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

21

Insulation Work

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

Unit L9 Electrical, Instrumentation & Control Erection

22

6.6 kV & 415V Switchgear, 415V MCC, 380V D/B, Aux Tx, Charger & UPS   Installation

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

23

Cable Tray Installation

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

275kV Switching Station Erection

24

Materials Delivery & Installation of GIS and Shunt Reactors

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

Miscellaneous

25

Slurry ash piping & filling

Noise

-                   General noise mitigation measures implemented and silent type equipment deployed.

 


 

1.4         Summary of EM&A Requirements

 

The EM&A program requires environmental monitoring for air, noise and water quality. As the post-project marine water monitoring was successfully completed in September 2002, no further water quality monitoring for the reclamation works would be required. The detailed EM&A monitoring work for air quality and noise are described in Sections 2 and 3 respectively. Regular environmental site audits for air quality, noise, water quality and waste management were carried out.  

 

The following environmental audits are summarized in Section 4 of this report:

 

·          Environmental monitoring results;

·          Waste Management Records;

·          Weekly site audit results;

·          The status of environmental licensing and permits for the Project;

·          The implementation status of environmental protection and pollution control/ mitigation measures.

 

Future key issues will be reported in Section 5 of this report.


 

 

Figure 1.1    Layout of Work Site


 

 

 

Figure 1.2    Cable Route of Transmission System


 

Figure 1.3 Location of Dumping Area



2.             AIR QUALITY

 

2.1         Monitoring Requirements

 

1-hour and 24-hour TSP monitoring at agreed frequencies were conducted to monitor air quality.  The impact monitoring data were checked against the Action/Limit Levels as determined in the Baseline Monitoring Report (Construction Phase).  Appendix B shows the established Action/Limit Levels for Air Quality.

 

 

2.2         Monitoring Locations

 

Three dust monitoring locations were selected for 1-hour TSP sampling (AM1, AM2 & AM3) while four monitoring locations were selected for 24-hour TSP sampling (AM1, AM2, AM3 and AM4).  Table 2.1 tabulates the monitoring stations.  The locations of the monitoring stations are shown in Figure 2.1.

 

Table 2.1    Air Quality Monitoring Locations