COVER

Table of Content

EXECUTIVE SUMMARY

1.             INTRODUCTION.. 1

1.1       Background  1

1.2       Project Organisation  1

1.3       Construction Works undertaken during the Reporting Month  2

1.4       Summary of EM&A Requirements  11

2.             AIR QUALITY.. 15

2.1       Monitoring Requirements  15

2.2       Monitoring Locations  15

2.3       Monitoring Equipment 15

2.4       Monitoring Parameters, Frequency and Duration  16

2.5       Monitoring Procedures and Calibration Details  16

2.6       Results and Observations  17

3.             NOISE.. 19

3.1       Monitoring Requirements  19

3.2       Monitoring Locations  19

3.3       Monitoring Equipment 19

3.4       Monitoring Parameters, Frequency and Duration  20

3.5       Monitoring Procedures and Calibration Details  20

3.6       Results and Observations  21

4.             ENVIRONMENTAL AUDIT.. 24

4.1       Review of Environmental Monitoring Procedures  24

4.2       Assessment of Environmental Monitoring Results  24

4.3       Site Environmental Audit 25

4.4       Status of Environmental Licensing and Permitting  25

4.5       Implementation Status of Environmental Mitigation Measures  28

4.6       Implementation Status of Event/Action Plans  28

4.7       Implementation Status of Environmental Complaint Handling Procedures  28

5.             FUTURE KEY ISSUES. 30

5.1       Status of Natural Gas supply  30

5.2       Key Issues for the Coming Month  30

5.3       Monitoring Schedules for the Next 3 Months  31

5.4       Construction Program for the Next 3 Months  31

6.             CONCLUSION.. 32

 


List of Tables

 

Table 1.1          Construction Activities and Their Corresponding Environmental Mitigation Measures

Table 2.1          Air Quality Monitoring Locations

Table 2.2          Air Quality Monitoring Equipment

Table 2.3          Air Quality Monitoring Parameter, Duration and Frequency

Table 3.1          Noise Monitoring Locations

Table 3.2          Noise Monitoring Equipment

Table 3.3          Noise Monitoring Duration and Parameter

Table 4.1          Summary of AL Level Exceedances on Monitoring Parameters

Table 4.2          Estimated Amounts of Waste Generated in November 2005

Table 4.3          Summary of Environmental Licensing and Permit Status

Table 4.4          Environmental Complaints / Enquiries Received in November 2005

Table 4.5          Outstanding Environmental Complaints / Enquiries Carried Over

 

 

List of figures

 

Figure 1.1         Layout of Work Site

Figure 1.2         Cable Route of Transmission System

Figure 1.3         Location of Dumping Area (South Cheung Chau Spoil Disposal Area)

Figure 2.1         Location of Air Quality Monitoring Stations

Figure 3.1         Location of Noise Monitoring Stations

Figure 3.2         Location of Manual Noise Monitoring

 

 

Appendices

 

Appendix A      Organization Chart

Appendix B      Action and Limit Levels for Air Quality and Noise

Appendix C      Environmental Monitoring Schedule

Appendix D      Air Quality Monitoring Results for November 2005

Appendix E      Noise Monitoring Results for November 2005

Appendix F      The QA/QC Procedures and Results

Appendix G      Event/Action Plans

Appendix H      Site Audit Summary

Appendix I       Summary of EMIS

Appendix J       Tentative Construction Programme

Appendix K     Supply and Installation of Submarine Gas Pipeline – Monthly EM&A Report for November 2005 prepared by the Consultant as one of the ET Members

 

 

                                                                                                         

 



EXECUTIVE SUMMARY

 

This is the fifty-sixth monthly Environmental Monitoring and Audit (EM&A) report for the Project “Construction of Lamma Power Station Extension” prepared by the Environmental Team (ET).  This report presents the results of impact monitoring on air quality and noise for the said project in November 2005.

 

After successful completion of post-project monitoring in September 2002, no further marine water quality monitoring for the reclamation works would be required.

 

Air and noise monitoring were performed. The results were checked against the established Action/Limit (AL) levels.  An on-site audit was conducted once per week. The implementation status of the environmental mitigation measures, Event/Action Plan and environmental complaint handling procedures were also checked.

 

A separate monthly EM&A report for submarine pipeline prepared by the consultant, as one of ET members, is shown in Appendix K.

 

Construction Activities Undertaken

 

Construction activities for Lamma Extension during the reporting month are tabulated as follows:

 

Item

Construction Activities

Unit L9 Civil and Building Works

Main Station Building, 275kV Switching Station Building, Shunt Reactor, Chimney, Drainage & Road, Fire Services Water Tank and Fire Pump House, C.W. Culvert System & Equipment Room, C.W. Pump Equipment Room, Gas Receiving Station, Pipe & Cable Rack and Lamma Power Station Addition and Alteration (LPS A&A) Works

Unit L9 Mechanical Erection

Erection of HRSG, Steam Turbine, Gas Turbine, Generator, Condenser, Aux Equipment, Air duct / Inlet Filter, HRSG Inlet Duct and Piping Support / Piping Erection; Insulation Work; and Installation of Platform, Pipe Rack and Intake Aux Equipment

Unit L9 Electrical, Instrumentation & Control Erection

Control Panel/Instrument Panel & Rack Installation, Cable Tray & Earthing Installation, Conduit & Instrument Piping Installation, Cable Laying & Termination and Busduct & Isolated Phase Busduct (IPB) Installation

275kV Switching Station Erection

Materials Delivery & Installation of GIS and Shunt Reactors

Transmission System

Construction of tunnel portal structure and installation of cable trough in cable tunnels 1 & 2

Gas Pipeline

Please refer to Appendix K

Miscellaneous

Slurry ash piping & filling

 


Environmental Monitoring Works

 

All monitoring work at designated stations was performed as scheduled satisfactorily.

 

Air Quality

 

No exceedance of Action/Limit levels on 1-hour TSP and 24-hour TSP for air quality was recorded in the month.

 

Noise

 

Construction work for Lamma Extension was carried out during the restricted hours including evening-time, holidays and night-time under valid Construction Noise Permits.  No exceedance of Action and Limit levels for noise arising from the construction of Lamma Extension and transmission system was recorded in the month. 

 

Site Environmental Audit

 

Independent Environmental Checker (IEC) conducted a site inspection on 23/11/2005.  The inspection result is attached in Appendix H.  EPD carried out a site visit for Lamma Extension gas pipeline construction work on 11/11/2005.  They had no adverse comment during the visit.

 

Site audits were carried out on a weekly basis to monitor environmental issues on the construction site.  The site conditions were generally satisfactory.  All required mitigation measures were implemented.

 

Environmental Licensing and Permitting

 

Description

Permit No.

Valid Period

Issued To

Date of Issuance

From

To

Varied Environmental Permit

EP-071/2000/C

18/05/05

-

HEC

18/05/05

Construction Noise Permit

GW-RS0317-05

26/05/05

25/11/05

Contractor

26/05/05

Construction Noise Permit

GW-RS0318-05

26/05/05

25/11/05

Contractor

26/05/05

Construction Noise Permit

GW-RS0416-05

10/07/05

09/01/06

Contractor

30/06/05

Construction Noise Permit

GW-RS0424-05

15/07/05

14/01/06

Contractor

07/07/05

Construction Noise Permit

GW-RS0514-05

12/08/05

11/02/06

Contractor

12/08/05

Construction Noise Permit

GW-RS0584-05

20/09/05

19/03/06

Contractor

15/09/05

Construction Noise Permit

GW-RS0585-05

17/09/05

16/03/06

Contractor

15/09/05

Construction Noise Permit

GW-RS0784-05

29/11/05

19/05/06

Contractor

29/11/05

Dumping Permit

EP/MD/06-031

05/09/05

04/03/06

Contractor

02/09/05

Dumping Permit

EP/MD/06-032

05/09/05

04/03/06

Contractor

02/09/05

Registration of Chemical Waste Producer

WPN5213-912-P2781-07

11/06/04

-

Contractor

11/06/04

Registration of Chemical Waste Producer

WPN5213-912-K2801-03

15/09/04

-

Contractor

15/09/04

Registration of Chemical Waste Producer

WPN5517-912-T2007-02

17/03/05

-

Contractor

17/03/05

Registration of Chemical Waste Producer

WPN5213-912-W2852-09

25/01/05

-

Contractor

25/01/05

Registration of Chemical Waste Producer

WPN4111-912-M2534-09

20/06/05

-

Contractor

20/06/05

WPCO Discharge Licence

EP890/W2/XD020

22/11/04

30/11/09

Contractor

22/11/04

 

Implementation Status of Environmental Mitigation Measures

Environmental mitigation measures for the construction activities as recommended in the EM&A manual were implemented in the reporting month.

 

Environmental Complaints

There was one general enquiry from a nearby resident of the Cyberport Landing Point site about dust and visual impact.  The enquirer was satisfied after being clarified of HEC’s dust suppression measures and work program.

 

Future Key Issues

The future key issues to be considered in the coming month are as follows:

 

Unit L9 Civil and Building Works

 

-         to continue monitoring the noise level during construction and to ensure compliance with the CNP’s already obtained;

-         to continue executing the preventive measures for avoiding noise exceedance and keep monitoring/ reviewing the performance;

-         to monitor and review the sufficiency of the dust suppression measures provided and increase the resources accordingly if necessary;

 

Unit L9 Mechanical Erection

 

-         to continue monitoring the noise level during construction

-         to continue executing the preventive measures for avoiding noise exceedance and keep monitoring/ reviewing the performance;

-         to monitor and review the sufficiency of the dust suppression measures provided and increase the resources accordingly if necessary;

 

Unit L9 Electrical Erection

 

-         to continue monitoring the noise level during construction

-         to continue executing the preventive measures for avoiding noise exceedance and keep monitoring/ reviewing the performance;

-         to monitor and review the sufficiency of the dust suppression measures provided and increase the resources accordingly if necessary;

 

275KV Switching Station Erection

 

-         to continue monitoring the noise level during construction

-         to continue executing the preventive measures for avoiding noise exceedance and keep monitoring/ reviewing the performance;

-         to monitor and review the sufficiency of the dust suppression measures provided and increase the resources accordingly if necessary;

 

Transmission System

 

-         to continue monitoring the noise level during construction;

-         to continue executing the preventive measures for avoiding noise exceedance and keep monitoring/ reviewing the performance;

-         to monitor and review the sufficiency of the dust suppression measures provided and increase the resources accordingly if necessary;

-         to closely monitor the construction activities in order to avoid disturbance to the rare plants; 

-         to provide temporary fire fighting equipment for prevention of fire within the work sites.

 

 

Concluding Remarks

The environmental performance of the project was generally satisfactory.




1.             INTRODUCTION

 

1.1         Background

 

The Environmental Team (hereinafter called the “ET”) was formed within the Hongkong Electric Co. Ltd (HEC) to undertake Environmental Monitoring and Audit for Construction of Lamma Power Station Extension” (hereinafter called the “Project”).  Under the requirements of Section 6 of Environmental Permit EP-071/2000/C, an EM&A programme for impact environmental monitoring set out in the EM&A Manual (Construction Phase) is required to be implemented.  In accordance with the EM&A Manual, environmental monitoring of air quality, noise and water quality and regular environmental audits are required for the Project. As the post-project marine water monitoring was successfully completed in September 2002, no further water quality monitoring for the reclamation works would be required.

 

The Project involves the construction of a gas-fired power station employing combined cycled gas turbine technology, forming an extension to the existing Lamma Power Station.  The key elements of the Project including the construction activities associated with the transmission system and submarine gas pipeline are outlined as follows.

 

·          dredging and reclamation to form approximately 22 hectares of usable area;

·          construction of six 300MW class gas-fired combined cycle units;

·          construction of a gas receiving station;

·          construction of a new transmission system linking the Lamma Extension to load centres on Hong Kong Island;

·          laying of a gas pipeline for the supply of natural gas to the new power station

 

This report summarizes the environmental monitoring and audit work for the Project for the month of November 2005.

 

 

1.2         Project Organisation

 

An Environmental Management Committee (EMC) has been set up in HEC to oversee the Project.  The management structure includes the following:

 

·          Environmental Protection Department (The Authority);

·          Environmental Manager (The Chairman of the Environmental Management Committee);

·          Engineer;

·          Independent Environmental Checker (IEC);

·          Environmental Team (ET);

·          Contractor.

 

The project organisation chart for the construction EM&A programme is shown in Appendix A.

 

 

1.3         Construction Works undertaken during the Reporting Month

 

Construction activities for Unit L9 civil and building works were for the Main Station Building, 275kV Switching Station Building, Shunt Reactor, Chimney, Drainage & Road, Fire Services Water Tank and Fire Pump House, C.W. Culvert System & Equipment Room, C.W. Pump Equipment Room, Gas Receiving Station, Pipe & Cable Rack and LPS A&A Works. Construction activities for Unit L9 mechanical works were the erection of HRSG, Steam Turbine, Gas Turbine, Generator, Condenser, Auxiliary Equipment, Air duct / Inlet Filter, HRSG Inlet Duct, Piping Support / Piping, Insulation Work, and installation of Platform, Pipe Rack, and Intake Auxiliary Equipment.  Construction activities for Unit L9 electrical, instrumentation & control erection were Control Panel / Instrument Panel & Rack installation, Cable Tray & Earthing installation, Conduit & Instrument Piping Installation, Cable Laying & Termination and Busduct & IPB Installation.  The construction activities for 275KV Switching Station erection were materials delivery & installation of GIS and Shunt Reactors.  Construction activities for Unit L9’s associated transmission system were construction of tunnel portal structure and installation of cable trough in cable tunnels 1 & 2, and the dredging/excavation of submarine cable trench outside N4 Landing Point.  A separate monthly EM&A report for submarine pipeline prepared by the consultant, as one of ET members, is shown in Appendix K.  Layout plans for construction site and transmission system are shown in Figure 1.1 and Figure 1.2 respectively.  Uncontaminated materials were dumped at the assigned location within the South Cheung Chau Spoil Disposal Area.  Figure 1.3 shows the dumping location in November 2005.

 

The main construction activities carried out during the reporting month and the corresponding environmental mitigation measures are summarized in Table 1.1.  The implementation of major mitigation measures in the month is provided in Appendix I.

 

Table 1.1    Construction Activities and Their Corresponding Environmental Mitigation Measures

 

Item

Construction Activities

Environmental Mitigation Measures

Unit L9 Civil and Building Works

1.

Main Station Building

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

2.

275kV Switching Station Building

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

3.

Shunt Reactor

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

4.

Chimney

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

5.

Drainage & Road Works

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

6.

Fire Services Water Tank and Fire Pump House

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

7.

C.W. Culvert System & Equipment Room

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

8.

C.W. Pump Equipment Room

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

9.

Gas Receiving Station

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

10.

Pipe & Cable Rack

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

11.

LPS A&A Works

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

Construction of Transmission System

12.

Construction of tunnel portal structure and installation of cable trough in cable tunnels 1 & 2

Air Quality

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Terrestrial Ecology

-                   Special care and close monitoring to avoid disturbances to the rare plant species.

-                   Temporary fire fighting equipment provided within the work area during construction.

Unit L9 Mechanical Erection

13.

HRSG Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

14.

Steam Turbine Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

15.

Gas Turbine Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

16.

Generator Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

17.

Condenser Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

18.

Auxiliary Equipment Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

19.

Air duct / Inlet Filter

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

20.

HRSG Inlet Duct

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

21.

Piping Support / Piping Erection

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

22.

Insulation Work

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

23.

Platform Installation

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

24.

Pipe Rack Installation

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

25.

Intake Aux Equipment Installation

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

Unit L9 Electrical, Instrumentation & Control Erection

26.

Control Panel/ Instrument

Panel & Rack Installation

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

27.

Cable Tray & Earthing Installation

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

28.

Conduit & Instrument Piping Installation

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

29.

Cable Laying & Termination

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

30.

Busduct & IPB Installation

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.

 

Waste Management

-                   Waste Management Plan submitted and implemented.

275kV Switching Station Erection

31.

Materials Delivery & Installation of GIS and Shunt Reactors

Air

-                   Dust suppression measures implemented.

 

Noise

-                   General noise mitigation measures employed at all work sites throughout the construction phase.