Table of Content
1.3 Construction Works undertaken during the Reporting Month
1.4 Summary of EM&A Requirements
2.4 Monitoring Parameters, Frequency and Duration
2.5 Monitoring Procedures and Calibration Details
3.4 Monitoring Parameters, Frequency and Duration
3.5 Monitoring Procedures and Calibration Details
4.1 Review of Environmental Monitoring Procedures
4.2 Assessment of Environmental Monitoring Results
4.4 Status of Environmental Licensing and Permitting
4.5 Implementation Status of Environmental Mitigation Measures
4.6 Implementation Status of Event/Action Plans
4.7 Implementation Status of Environmental Complaint Handling Procedures
5.1 Status of Natural Gas supply
5.2 Key Issues for the Coming Month
5.3 Monitoring Schedules for the Next 3 Months
5.4 Construction Program for the Next 3 Months
List of Tables
Table 1.1 Construction
Activities and Their Corresponding Environmental Mitigation Measures
Table 2.1 Air Quality Monitoring Locations
Table 2.2 Air Quality Monitoring Equipment
Table 2.3 Air Quality Monitoring Parameter, Duration and Frequency
Table 3.1 Noise
Monitoring Locations
Table 3.2 Noise
Monitoring Equipment
Table 3.3 Noise
Monitoring Duration and Parameter
Table 4.1 Summary
of AL Level Exceedances on Monitoring Parameters
Table 4.2 Estimated
Amounts of Waste Generated in November 2005
Table 4.3 Summary
of Environmental Licensing
and Permit Status
Table
4.4 Environmental
Complaints / Enquiries Received in November 2005
Table
4.5 Outstanding
Environmental Complaints / Enquiries Carried Over
List of figures
Figure
1.1 Layout
of Work Site
Figure
1.2 Cable
Route of Transmission System
Figure
1.3 Location
of Dumping Area (South Cheung Chau Spoil Disposal Area)
Figure
2.1 Location
of Air Quality Monitoring Stations
Figure
3.1 Location
of Noise Monitoring Stations
Figure
3.2 Location
of Manual Noise Monitoring
Appendices
Appendix B Action and Limit Levels for Air Quality and Noise
Appendix C Environmental
Monitoring Schedule
Appendix D Air
Quality Monitoring Results for November 2005
Appendix E Noise
Monitoring Results for November 2005
Appendix F The
QA/QC Procedures and Results
Appendix J Tentative
Construction Programme
This is the fifty-sixth monthly Environmental Monitoring and Audit (EM&A)
report for the Project “Construction of Lamma Power Station Extension” prepared
by the Environmental Team (ET).
This report presents the results of impact monitoring on air quality and noise for the said project in November
2005.
After successful completion of post-project
monitoring in September 2002, no further marine water quality monitoring for
the reclamation works would be required.
Air and noise monitoring were performed. The results were checked
against the established
Action/Limit (AL) levels.
An on-site audit was conducted once per week. The implementation status of the environmental
mitigation measures, Event/Action
Plan and environmental complaint handling procedures were also checked.
A separate monthly
EM&A report for submarine pipeline prepared by the consultant, as one of ET
members, is shown in Appendix K.
Construction
Activities Undertaken
Construction
activities for Lamma Extension during the reporting month are tabulated as
follows:
|
Item |
Construction
Activities |
|
Unit L9 Civil and Building Works |
Main Station Building, 275kV Switching Station
Building, Shunt
Reactor, Chimney, Drainage
& Road,
Fire Services Water Tank and Fire
Pump House, C.W. Culvert System &
Equipment Room, C.W. Pump Equipment Room, Gas Receiving Station, Pipe & Cable
Rack and Lamma Power Station Addition and Alteration (LPS A&A) Works |
|
Unit L9 Mechanical Erection |
Erection of HRSG, Steam Turbine, Gas Turbine, Generator,
Condenser, Aux Equipment, Air duct / Inlet Filter, HRSG Inlet Duct and
Piping Support / Piping Erection; Insulation Work; and Installation of
Platform, Pipe Rack and Intake Aux Equipment |
|
Unit L9 Electrical, Instrumentation & Control
Erection |
Control Panel/Instrument Panel & Rack
Installation, Cable Tray & Earthing Installation, Conduit & Instrument Piping
Installation, Cable Laying & Termination
and Busduct & Isolated Phase Busduct (IPB) Installation |
|
275kV Switching
Station Erection |
Materials Delivery & Installation
of GIS and Shunt Reactors |
|
Transmission System |
Construction
of tunnel portal structure and installation of cable trough in cable tunnels 1 & 2 |
|
Gas Pipeline |
Please refer to Appendix K |
|
Miscellaneous |
Slurry ash
piping & filling |
Environmental
Monitoring Works
All monitoring work at
designated stations was performed as scheduled satisfactorily.
Air Quality
No exceedance
of Action/Limit levels on 1-hour TSP and 24-hour TSP for air quality was recorded in the month.
Noise
Construction work for Lamma Extension was carried out during the
restricted hours including evening-time, holidays and night-time
under valid Construction Noise Permits.
No exceedance
of Action and Limit levels for noise arising from
the construction of Lamma Extension and transmission system was recorded
in the month.
Site Environmental Audit
Independent Environmental
Checker (IEC) conducted a site inspection on 23/11/2005. The inspection result is
attached in Appendix H. EPD carried out a site visit for Lamma Extension gas pipeline construction work on 11/11/2005. They had no adverse comment during the visit.
Site audits
were carried out on a weekly basis to monitor environmental issues on the construction site. The site conditions were generally
satisfactory. All required
mitigation measures were implemented.
Environmental Licensing and Permitting
|
Description |
Permit No. |
Valid Period |
Issued To |
Date of Issuance |
|
|
From |
To |
||||
|
Varied Environmental Permit |
EP-071/2000/C |
18/05/05 |
- |
HEC |
18/05/05 |
|
Construction Noise Permit |
GW-RS0317-05 |
26/05/05 |
25/11/05 |
Contractor |
26/05/05 |
|
Construction Noise Permit |
GW-RS0318-05 |
26/05/05 |
25/11/05 |
Contractor |
26/05/05 |
|
Construction Noise Permit |
GW-RS0416-05 |
10/07/05 |
09/01/06 |
Contractor |
30/06/05 |
|
Construction Noise Permit |
GW-RS0424-05 |
15/07/05 |
14/01/06 |
Contractor |
07/07/05 |
|
Construction Noise Permit |
GW-RS0514-05 |
12/08/05 |
11/02/06 |
Contractor |
12/08/05 |
|
Construction Noise Permit |
GW-RS0584-05 |
20/09/05 |
19/03/06 |
Contractor |
15/09/05 |
|
Construction Noise Permit |
GW-RS0585-05 |
17/09/05 |
16/03/06 |
Contractor |
15/09/05 |
|
Construction Noise Permit |
GW-RS0784-05 |
29/11/05 |
19/05/06 |
Contractor |
29/11/05 |
|
Dumping Permit |
EP/MD/06-031 |
05/09/05 |
04/03/06 |
Contractor |
02/09/05 |
|
Dumping Permit |
EP/MD/06-032 |
05/09/05 |
04/03/06 |
Contractor |
02/09/05 |
|
Registration
of Chemical Waste Producer |
WPN5213-912-P2781-07 |
11/06/04 |
- |
Contractor |
11/06/04 |
|
Registration
of Chemical Waste Producer |
WPN5213-912-K2801-03 |
15/09/04 |
- |
Contractor |
15/09/04 |
|
Registration
of Chemical Waste Producer |
WPN5517-912-T2007-02 |
17/03/05 |
- |
Contractor |
17/03/05 |
|
Registration
of Chemical Waste Producer |
WPN5213-912-W2852-09 |
25/01/05 |
- |
Contractor |
25/01/05 |
|
Registration
of Chemical Waste Producer |
WPN4111-912-M2534-09 |
20/06/05 |
- |
Contractor |
20/06/05 |
|
WPCO
Discharge Licence |
EP890/W2/XD020 |
22/11/04 |
30/11/09 |
Contractor |
22/11/04 |
Implementation
Status of Environmental Mitigation Measures
Environmental
mitigation measures for the construction activities
as recommended
in the EM&A manual were implemented in the reporting month.
Environmental
Complaints
There was one general enquiry from
a nearby resident of the Cyberport Landing Point site about dust and visual
impact. The enquirer was
satisfied after being clarified of HEC’s dust suppression measures and work
program.
Future Key
Issues
The future key issues to be
considered in the coming month are as follows:
Unit L9 Civil and Building
Works
-
to continue monitoring the noise level during construction and to
ensure compliance with the CNP’s already obtained;
-
to continue executing the preventive measures for avoiding noise
exceedance and keep monitoring/ reviewing the performance;
-
to monitor and review the
sufficiency of the dust suppression measures provided and increase the
resources accordingly if necessary;
Unit L9 Mechanical Erection
-
to continue monitoring the noise level during construction
-
to continue executing the preventive measures for avoiding noise
exceedance and keep monitoring/ reviewing the performance;
-
to monitor and review the
sufficiency of the dust suppression measures provided and increase the
resources accordingly if necessary;
Unit L9 Electrical Erection
-
to continue monitoring the noise level during construction
-
to continue executing the preventive measures for avoiding noise
exceedance and keep monitoring/ reviewing the performance;
-
to monitor and review the
sufficiency of the dust suppression measures provided and increase the
resources accordingly if necessary;
275KV Switching Station Erection
-
to continue monitoring the noise level during construction
-
to continue executing the preventive measures for avoiding noise
exceedance and keep monitoring/ reviewing the performance;
-
to monitor and review the
sufficiency of the dust suppression measures provided and increase the
resources accordingly if necessary;
Transmission System
-
to continue monitoring the noise level during construction;
-
to continue executing the
preventive measures for avoiding noise exceedance and keep monitoring/
reviewing the performance;
-
to monitor and review the
sufficiency of the dust suppression measures provided and increase the
resources accordingly if necessary;
-
to closely monitor the construction
activities in order to avoid disturbance to the rare plants;
-
to provide temporary fire
fighting equipment for prevention of fire within the work sites.
Concluding Remarks
The environmental performance of the project was
generally satisfactory.
The Environmental Team (hereinafter called the “ET”) was formed within the Hongkong Electric Co. Ltd (HEC) to undertake Environmental Monitoring and Audit for “Construction of Lamma Power Station Extension” (hereinafter called the “Project”). Under the requirements of Section 6 of Environmental Permit EP-071/2000/C, an EM&A programme for impact environmental monitoring set out in the EM&A Manual (Construction Phase) is required to be implemented. In accordance with the EM&A Manual, environmental monitoring of air quality, noise and water quality and regular environmental audits are required for the Project. As the post-project marine water monitoring was successfully completed in September 2002, no further water quality monitoring for the reclamation works would be required.
The Project
involves the construction of a gas-fired power station employing combined
cycled gas turbine technology, forming an extension to the existing Lamma Power
Station. The key elements of the
Project including the construction activities associated with the transmission
system and submarine gas pipeline are outlined as follows.
· dredging and reclamation to form approximately 22 hectares of usable area;
· construction of six 300MW class gas-fired combined cycle units;
· construction of a gas receiving station;
· construction of a new transmission system linking the Lamma Extension to load centres on Hong Kong Island;
· laying of a gas pipeline for the supply of natural gas to the new power station
This report summarizes the environmental monitoring and audit work for
the Project for the month of November 2005.
An Environmental Management Committee
(EMC) has been set up in HEC to oversee the Project. The management structure includes the following:
· Environmental Protection Department (The Authority);
· Environmental Manager (The Chairman of the Environmental Management Committee);
· Engineer;
· Independent Environmental Checker (IEC);
· Environmental Team (ET);
· Contractor.
The project organisation chart for the construction EM&A programme is shown in Appendix A.
1.3
Construction Works undertaken during the Reporting
Month
Construction activities for Unit L9 civil and building works were for the Main Station Building, 275kV Switching Station Building, Shunt Reactor, Chimney, Drainage & Road, Fire Services Water Tank and Fire Pump House, C.W. Culvert System & Equipment Room, C.W. Pump Equipment Room, Gas Receiving Station, Pipe & Cable Rack and LPS A&A Works. Construction activities for Unit L9 mechanical works were the erection of HRSG, Steam Turbine, Gas Turbine, Generator, Condenser, Auxiliary Equipment, Air duct / Inlet Filter, HRSG Inlet Duct, Piping Support / Piping, Insulation Work, and installation of Platform, Pipe Rack, and Intake Auxiliary Equipment. Construction activities for Unit L9 electrical, instrumentation & control erection were Control Panel / Instrument Panel & Rack installation, Cable Tray & Earthing installation, Conduit & Instrument Piping Installation, Cable Laying & Termination and Busduct & IPB Installation. The construction activities for 275KV Switching Station erection were materials delivery & installation of GIS and Shunt Reactors. Construction activities for Unit L9’s associated transmission system were construction of tunnel portal structure and installation of cable trough in cable tunnels 1 & 2, and the dredging/excavation of submarine cable trench outside N4 Landing Point. A separate monthly EM&A report for submarine pipeline prepared by the consultant, as one of ET members, is shown in Appendix K. Layout plans for construction site and transmission system are shown in Figure 1.1 and Figure 1.2 respectively. Uncontaminated materials were dumped at the assigned location within the South Cheung Chau Spoil Disposal Area. Figure 1.3 shows the dumping location in November 2005.
The main construction activities carried out during the reporting month and the corresponding environmental mitigation measures are summarized in Table 1.1. The implementation of major mitigation measures in the month is provided in Appendix I.
Table 1.1 Construction Activities and Their Corresponding Environmental Mitigation Measures
|
Item |
Construction Activities |
Environmental Mitigation Measures |
|
Unit L9 Civil and Building Works |
||
|
1. |
Main
Station Building |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
2. |
275kV
Switching Station Building |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
3. |
Shunt
Reactor |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
4. |
Chimney |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
5. |
Drainage
& Road Works |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
6. |
Fire Services Water Tank and Fire Pump House |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
7. |
C.W.
Culvert System & Equipment Room |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
8. |
C.W. Pump
Equipment Room |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
9. |
Gas Receiving Station |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
10. |
Pipe
& Cable Rack |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
11. |
LPS
A&A Works |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
Construction of
Transmission System
|
||
|
12. |
Construction of
tunnel portal structure and installation of cable trough in cable tunnels 1 & 2 |
Air Quality
- Dust suppression measures implemented. Noise
- General noise mitigation measures employed at all work sites throughout the construction phase. Terrestrial Ecology
- Special care and close monitoring to avoid disturbances to the rare plant species. -
Temporary fire fighting equipment provided within the
work area during construction. |
Unit L9
Mechanical Erection
|
||
|
13. |
HRSG Erection |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
14. |
Steam
Turbine Erection |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
15. |
Gas Turbine
Erection |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
16. |
Generator
Erection |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
17. |
Condenser
Erection |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
18. |
Auxiliary
Equipment Erection |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
19. |
Air duct /
Inlet Filter |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
20. |
HRSG Inlet
Duct |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
21. |
Piping
Support / Piping Erection |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
22. |
Insulation
Work |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
23. |
Platform
Installation |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
24. |
Pipe Rack
Installation |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
25. |
Intake Aux Equipment
Installation |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
Unit L9
Electrical, Instrumentation & Control Erection
|
||
|
26. |
Control Panel/ Instrument Panel & Rack Installation |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
27. |
Cable Tray & Earthing Installation |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
28. |
Conduit
& Instrument Piping Installation |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
29. |
Cable Laying & Termination |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
|
30. |
Busduct & IPB Installation |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and implemented. |
275kV Switching Station Erection
|
||
|
31. |
Materials Delivery & Installation of GIS and Shunt
Reactors |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation measures employed at all
work sites throughout the construction phase. |