Table of Content
1.3 Construction Works undertaken during the Reporting Month
1.4 Summary of
EM&A Requirements
2.4 Monitoring Parameters, Frequency and Duration
2.5 Monitoring Procedures and Calibration Details
3.4 Monitoring
Parameters, Frequency and Duration
3.5 Monitoring Procedures and
Calibration Details
4.1 Review of Environmental Monitoring Procedures
4.2 Assessment of Environmental Monitoring Results
4.4 Status of
Environmental Licensing and Permitting
4.5 Implementation Status of Environmental Mitigation Measures
4.6 Implementation
Status of Event/Action Plans
4.7 Implementation
Status of Environmental Complaint Handling Procedures
5.1 Status of Natural Gas supply
5.2 Key Issues for
the Coming Month
5.3 Monitoring
Schedules for the Next 3 Months
5.4 Construction
Program for the Next 3 Months
List
of Tables
Table
1.1......... Construction Activities and Their Corresponding
Environmental Mitigation Measures
Table 2.1......... Air Quality Monitoring Locations
Table 2.2......... Air Quality Monitoring Equipment
Table 2.3......... Air Quality Monitoring Parameter, Duration and Frequency
Table 3.1......... Noise Monitoring Locations
Table 3.2......... Noise Monitoring Equipment
Table 3.3......... Noise Monitoring Duration and Parameter
Table 4.1......... Summary of AL Level Exceedances on Monitoring Parameters
Table 4.2......... Estimated Amounts of Waste Generated in May 2006
Table 4.3......... Summary of Environmental Licensing and Permit Status
Table 4.4......... Environmental Complaints / Enquiries Received in May 2006
Table 4.5......... Outstanding Environmental Complaints / Enquiries
Carried Over
List of figures
Figure 1.1 Layout of Work
Site
Figure 1.2 Cable Route of
Transmission System
Figure 1.3 Location of
Dumping Area (up to 16/05/2006)
Figure 1.4 Location of Dumping Area (from 17/05/2006)
Figure 2.1 Location of Air
Quality Monitoring Stations
Figure 3.1 Location of
Noise Monitoring Stations
Figure 3.2 Location of
Manual Noise Monitoring
Appendices
Appendix B Action and Limit Levels for Air Quality and Noise
Appendix C Environmental
Monitoring Schedule
Appendix D Air Quality Monitoring
Results for May 2006
Appendix E Noise Monitoring Results
for May 2006
Appendix F The QA/QC Procedures and
Results
Appendix J Tentative Construction Programme
This is the sixty-second monthly Environmental
Monitoring and Audit (EM&A) report for the Project “Construction of
Lamma Power Station Extension” prepared by the Environmental Team
(ET). This report presents the results of impact monitoring on air quality and
noise for the said project in May
2006.
After successful completion of
post-project monitoring in September 2002, no further marine water quality
monitoring for the reclamation works would be required.
Air and noise monitoring were performed. The
results were checked against
the established Action/Limit (AL) levels. An on-site audit was conducted once per week.
The implementation status
of the environmental mitigation measures, Event/Action
Plan and environmental complaint handling procedures were also checked.
A
separate monthly EM&A report for submarine pipeline prepared by the
consultant, as one of ET members, is shown in Appendix K.
Construction
Activities Undertaken
Construction
activities for Lamma Extension during the reporting month are tabulated as
follows:
|
Item |
Construction
Activities |
|
Unit L9 Civil and Building Works |
Main Station Building, 275kV Switching Station Building, Shunt
Reactor, Chimney, Drainage
& Road,
Fire Services Water Tank and Fire Pump
House, C.W. Culvert System &
Equipment Room, C.W. Pump Equipment Room, Gas Receiving Station, Pipe & Cable
Rack and Lamma Power Station Addition and Alteration (LPS A&A) Works |
|
Unit L9 Mechanical Erection |
Erection of HRSG, Steam Turbine, Gas Turbine,
Generator, Condenser, Aux Equipment, Air duct /
Inlet Filter, HRSG Inlet Duct and Piping Support / Piping Erection;
Insulation Work; and Installation of Platform, Pipe Rack, Intake Aux
Equipment, Bop piping and GRS piping |
|
Unit L9 Electrical, Instrumentation & Control
Erection |
Cable
Tray Cover Installation, Instrument Piping Installation and Cable Termination
|
|
Transmission System |
Backfilling
above portal structure for Cable Duct
2 and cable trench from N4 landing point to Cable Duct no.2 Entrance |
|
Gas Pipeline |
Please refer to Appendix
K |
|
Miscellaneous |
Slurry ash
piping & filling |
Environmental
Monitoring Works
One (1) dust monitoring events was re-scheduled in the reporting month
as shown in the following table:
|
Monitoring work |
Monitoring Location |
Original Schedule |
Makeup Sampling |
Reasons |
|
1 hour TSP sampling |
AM3 |
02/05/2006 |
03/05/2006 |
Failure of TEOM TSP sampler. |
Other than the above
incident, all monitoring work at designated stations was performed as scheduled
satisfactorily.
Air Quality
No exceedance of Action/Limit levels on 1-hour TSP and 24-hour TSP for air quality was recorded in the month.
Noise
Construction work for Lamma Extension was carried out during the restricted hours including evening-time, holidays and night-time under valid Construction
Noise Permits. No exceedance of Action
and Limit levels
for noise arising from the construction of Lamma
Extension and transmission system was recorded in the month.
Site Environmental Audit
EPD officials from Regional Office (South) visited
Lamma Power Station on 29/05/2006. EPD inspected the Lamma Extension Construction
Site. There was no adverse comment from
EPD regarding the construction site.
Independent Environmental Checker (IEC) conducted a
site inspection on 25/05/2006. The
inspection result is attached in Appendix H.
Site audits
were carried out on a weekly basis to monitor environmental issues on the construction site. The site conditions were generally
satisfactory. All required mitigation
measures were implemented.
Environmental Licensing and Permitting
|
Description |
Permit No. |
Valid Period |
Issued To |
Date of Issuance |
|
|
From |
To |
||||
|
Varied Environmental
Permit |
EP-071/2000/C |
18/05/05 |
- |
HEC |
18/05/05 |
|
Construction Noise
Permit |
GW-RS0784-05 |
29/11/05 |
19/05/06 |
Contractor |
29/11/05 |
|
Construction Noise
Permit |
GW-RS0719-05 |
01/12/05 |
31/05/06 |
Contractor |
09/11/05 |
|
Construction Noise
Permit |
GW-RE0363-05 |
01/01/06 |
31/05/06 |
Contractor |
24/11/05 |
|
Construction Noise
Permit |
GW-RS0008-06 |
24/01/06 |
30/06/06 |
Contractor |
20/01/06 |
|
Construction Noise
Permit |
GW-RS0032-06 |
11/02/06 |
10/08/06 |
Contractor |
27/01/06 |
|
Construction Noise
Permit |
GW-RS0138-06 |
24/03/06 |
21/09/06 |
Contractor |
24/03/06 |
|
Construction Noise
Permit |
GW-RS0154-06 |
04/04/06 |
30/06/06 |
Contractor |
31/03/06 |
|
Construction Noise
Permit |
GW-RS0278-06 |
24/05/06 |
19/11/06 |
Contractor |
24/05/06 |
|
Dumping Permit |
EP/MD/06-092 |
19/04/06 |
30/06/06 |
Contractor |
19/04/06 |
|
Registration of
Chemical Waste Producer |
WPN5213-912-P2781-07 |
11/06/04 |
- |
Contractor |
11/06/04 |
|
Registration
of Chemical Waste Producer |
WPN5213-912-K2801-03 |
15/09/04 |
- |
Contractor |
15/09/04 |
|
Registration
of Chemical Waste Producer |
WPN5517-912-T2007-02 |
17/03/05 |
- |
Contractor |
17/03/05 |
|
Registration
of Chemical Waste Producer |
WPN5213-912-W2852-09 |
25/01/05 |
- |
Contractor |
25/01/05 |
|
Registration
of Chemical Waste Producer |
WPN4111-912-M2534-09 |
20/06/05 |
- |
Contractor |
20/06/05 |
|
WPCO
Discharge Licence |
EP890/W2/XD020 |
22/11/04 |
30/11/09 |
Contractor |
22/11/04 |
|
WPCO
Discharge Licence |
EP890/W2/XD021 |
03/02/05 |
28/02/10 |
Contractor |
03/02/05 |
Implementation Status
of Environmental Mitigation Measures
Environmental
mitigation measures for the construction activities
as recommended
in the EM&A manual were implemented in the reporting month.
Environmental
Complaints
No complaint against the
construction activities was received in the reporting month. All previous cases
were settled.
Future Key
Issues
The future key issues to be
considered in the coming month are as follows:
Unit L9 Civil and Building
Works
-
to continue
monitoring the noise level during construction and to ensure compliance with
the CNP’s already obtained;
-
to continue executing the preventive
measures for avoiding noise exceedance and keep monitoring/ reviewing the
performance;
-
to monitor and
review the sufficiency of the dust suppression measures provided and increase
the resources accordingly if necessary;
Unit L9 Mechanical Erection
-
to continue
monitoring the noise level during construction
-
to continue executing the preventive measures
for avoiding noise exceedance and keep monitoring/ reviewing the performance;
-
to monitor and
review the sufficiency of the dust suppression measures provided and increase
the resources accordingly if necessary;
Unit L9 Electrical Erection
-
to continue
monitoring the noise level during construction
-
to continue executing the preventive
measures for avoiding noise exceedance and keep monitoring/ reviewing the
performance;
-
to monitor and
review the sufficiency of the dust suppression measures provided and increase
the resources accordingly if necessary;
Transmission System
-
to continue
monitoring the noise level during construction;
-
to continue
executing the preventive measures for avoiding noise exceedance and keep
monitoring/ reviewing the performance;
-
to monitor and
review the sufficiency of the dust suppression measures provided and increase
the resources accordingly if necessary;
-
to closely monitor
the construction activities in order to avoid disturbance to the rare
plants;
-
to provide temporary
fire fighting equipment for prevention of fire within the work sites.
Concluding
Remarks
The environmental performance of the project was
generally satisfactory.
The Environmental Team (hereinafter called the “ET”) was formed within the Hongkong Electric Co. Ltd (HEC) to undertake Environmental Monitoring and Audit for “Construction of Lamma Power Station Extension” (hereinafter called the “Project”). Under the requirements of Section 6 of Environmental Permit EP-071/2000/C, an EM&A programme for impact environmental monitoring set out in the EM&A Manual (Construction Phase) is required to be implemented. In accordance with the EM&A Manual, environmental monitoring of air quality, noise and water quality and regular environmental audits are required for the Project. As the post-project marine water monitoring was successfully completed in September 2002, no further water quality monitoring for the reclamation works would be required.
The
Project involves the construction of a gas-fired power station employing
combined cycled gas turbine technology, forming an extension to the existing
Lamma Power Station. The key elements of
the Project including the construction activities associated with the
transmission system and submarine gas pipeline are outlined as follows.
· dredging and reclamation to form approximately 22 hectares of usable area;
· construction of six 300MW class gas-fired combined cycle units;
· construction of a gas receiving station;
·
construction of a new
transmission system linking the Lamma Extension to load centres on
· laying of a gas pipeline for the supply of natural gas to the new power station
This report summarizes the environmental
monitoring and audit work for the Project for the month of May 2006.
An Environmental Management
Committee (EMC) has been set up in HEC to oversee the Project. The management structure includes the
following:
· Environmental Protection Department (The Authority);
· Environmental Manager (The Chairman of the Environmental Management Committee);
· Engineer;
· Independent Environmental Checker (IEC);
· Environmental Team (ET);
· Contractor.
The project organisation chart for the construction EM&A programme is shown in Appendix A.
1.3
Construction Works undertaken
during the Reporting Month
Construction activities for Unit L9 civil and building
works were for the
The main construction activities carried out during the reporting month and the corresponding environmental mitigation measures are summarized in Table 1.1. The implementation of major mitigation measures in the month is provided in Appendix I.
Table 1.1 Construction Activities and Their Corresponding Environmental Mitigation Measures
|
Item |
Construction Activities |
Environmental Mitigation Measures |
|
Unit L9 Civil and Building Works |
||
|
1 |
|
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation measures
employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and
implemented. |
|
2 |
275kV
Switching |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and
implemented. |
|
3 |
Shunt
Reactor |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation measures
employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
4 |
Chimney |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation measures
employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
5 |
Drainage
& Road Works |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation measures
employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
6 |
Fire Services Water Tank and Fire Pump House |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
7 |
C.W.
Culvert System & Equipment Room |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
8 |
C.W. Pump Equipment Room |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
9 |
Gas Receiving Station |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
10 |
Pipe
& Cable Rack |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
11 |
LPS
A&A Works |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
Construction of
Transmission System
|
||
|
12 |
Backfilling above portal structure for Cable Duct 2 and cable trench from N4 landing point to Cable Duct no.2 Entrance |
Terrestrial Ecology
- Special care and close monitoring to avoid disturbances to the rare plant species. -
Temporary fire fighting
equipment provided within the work area during construction. |
|
13 |
Installation
of Submarine Cables between N2 & N4 |
Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. |
|
14 |
Backfilling & Cable Protection |
Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. |
Unit L9 Mechanical
Erection
|
||
|
15 |
HRSG
Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
16 |
Steam
Turbine Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
17 |
Gas Turbine
Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
18 |
Generator
Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
19 |
Condenser
Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
20 |
Auxiliary
Equipment Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
21 |
Air duct /
Inlet Filter |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
22 |
HRSG Inlet
Duct |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
23 |
Piping
Support / Piping Erection |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
24 |
Insulation
Work |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
25 |
Platform
Installation |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
26 |
Pipe Rack
Installation |
Air
-
Dust suppression measures implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
27 |
Intake Aux
Equipment Installation |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
28 |
Bop piping
installation |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
29 |
GRS piping
installation |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
Unit L9 Electrical,
Instrumentation & Control Erection
|
||
|
30 |
Cable Tray Cover Installation |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted
and implemented. |
|
31 |
Instrument
Piping Installation |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
32 |
Cable Termination |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
Miscellaneous
|
||
|
33 |
Slurry
ash piping & filling |
Noise
- General noise mitigation measures implemented and silent type equipment deployed. |
1.4 Summary of EM&A Requirements
The EM&A program requires environmental monitoring for air,
noise and water
quality. As the post-project marine water monitoring was successfully
completed in September 2002, no further water quality monitoring for the
reclamation works would be required. The detailed EM&A monitoring work for air quality and noise are described in Sections 2 and 3
respectively. Regular environmental site audits for air quality, noise, water quality and waste management were carried out.
The following environmental
audits are summarized in Section 4 of this report:
· Environmental monitoring results;
· Waste Management Records;
· Weekly site audit results;
· The status of environmental licensing and permits for the Project;
· The implementation status of environmental protection and pollution control/ mitigation measures.
Future key issues will be reported in Section 5 of this report.
1-hour and 24-hour TSP monitoring at agreed frequencies were conducted to monitor air quality. The impact monitoring data were checked against
the Action/Limit Levels
as determined in the Baseline Monitoring Report (Construction Phase). Appendix B shows the established
Action/Limit Levels for Air Quality.
Three
dust monitoring locations were selected for 1-hour TSP sampling (AM1, AM2 &
AM3) while four monitoring locations were selected for 24-hour TSP sampling
(AM1, AM2, AM3 and AM4). Table
2.1 tabulates the monitoring stations.
The locations of the monitoring stations are shown in Figure
2.1.
Table 2.1 Air Quality Monitoring Locations
|
Location I.D. |
Description |
|
AM1 |
Reservoir |
|
AM2 |
East Gate |
|
AM3 |
Ash Lagoon |
|
AM4 |
|
Continuous
24-hour TSP air quality monitoring was performed using the GS2310 High Volume
Air Samplers (HVAS), Partisol Model 2000 Sampler and the MINIVOL Portable
Sampler at AM1&2, AM3 and AM4 respectively.
TEOM Model 1400a continuous dust monitors were used to carry out 1-hour
TSP monitoring at AM1, AM2 and AM3. Table 2.2 summarises the equipment used in dust monitoring.
Table 2.2 Air Quality Monitoring Equipment
|
Equipment |
Model and Make |
|
24-hour
sampling: HVAS
Sampler Partisol
Air Sampler MINIVOL
Portable Sampler 1-hour
sampling: Continuous
TSP Dust Meter |
Model GS2310 Anderson Instruments Inc. Partisol Model 2000 Rupprecht & Patashnick AIRMETRICS TEOM Model 1400a Rupprecht & Patashnick |
2.4
Monitoring
Parameters, Frequency and Duration
Table 2.3 summarises the monitoring parameters, duration and
frequency of air quality monitoring. The
monitoring schedule for the reporting month is shown in Appendix
C.
Table 2.3 Air Quality Monitoring Parameter,
Duration and Frequency
|
Monitoring Stations |
Parameter |
Duration |
Frequency |
|
AM1 |
1-hour TSP |
1 |
3 hourly samples every 6
days |
|
24-hour TSP |
24 |
Once every 6 days |
|
|
AM2 |