Table of Content
1.3 Construction Works undertaken during the Reporting Month
1.4 Summary of
EM&A Requirements
2.4 Monitoring Parameters, Frequency and Duration
2.5 Monitoring Procedures and Calibration Details
3.4 Monitoring
Parameters, Frequency and Duration
3.5 Monitoring Procedures and
Calibration Details
4.1 Review of Environmental Monitoring Procedures
4.2 Assessment of Environmental Monitoring Results
4.4 Status of
Environmental Licensing and Permitting
4.5 Implementation Status of Environmental Mitigation Measures
4.6 Implementation
Status of Event/Action Plans
4.7 Implementation
Status of Environmental Complaint Handling Procedures
5.1 Status of Natural Gas supply
5.2 Key Issues for
the Coming Month
5.3 Monitoring
Schedules for the Next 3 Months
5.4 Construction
Program for the Next 3 Months
List
of Tables
Table
1.1......... Construction Activities and Their Corresponding
Environmental Mitigation Measures
Table 2.1......... Air Quality Monitoring Locations
Table 2.2......... Air Quality Monitoring Equipment
Table 2.3......... Air Quality Monitoring Parameter, Duration and Frequency
Table 3.1......... Noise Monitoring Locations
Table 3.2......... Noise Monitoring Equipment
Table 3.3......... Noise Monitoring Duration and Parameter
Table 4.1......... Summary of AL Level Exceedances on Monitoring Parameters
Table 4.2......... Estimated Amounts of Waste Generated in July 2006
Table 4.3......... Summary of Environmental Licensing and Permit Status
Table 4.4......... Environmental Complaints / Enquiries Received in July 2006
Table 4.5......... Outstanding Environmental Complaints / Enquiries
Carried Over
List of figures
Figure 1.1 Layout of Work Site
Figure 1.2 Cable Route of
Transmission System
Figure 2.1 Location of Air Quality
Monitoring Stations
Figure 3.1 Location of Noise
Monitoring Stations
Figure 3.2 Location of Manual
Noise Monitoring
Appendices
Appendix B Action and Limit Levels for Air Quality and Noise
Appendix C Environmental
Monitoring Schedule
Appendix D Air Quality Monitoring Results
for July 2006
Appendix E Noise Monitoring Results
for July 2006
Appendix F The QA/QC Procedures and
Results
Appendix J Tentative Construction Programme
This is the sixty-fourth monthly
Environmental Monitoring and Audit (EM&A) report for the Project
“Construction of Lamma Power Station Extension” prepared by the
Environmental Team (ET). This report presents the results of impact monitoring on air quality and
noise for the said project in July
2006.
After successful completion of post-project
monitoring in September 2002, no further marine water quality monitoring for
the reclamation works would be required.
Air and noise monitoring were performed. The
results were checked against
the established Action/Limit (AL) levels. An on-site audit was conducted once per week.
The implementation status
of the environmental mitigation measures, Event/Action
Plan and environmental complaint handling procedures were also checked.
Construction
Activities Undertaken
Construction activities
for Lamma Extension during the reporting month are tabulated as follows:
|
Item |
Construction
Activities |
|
Unit L9 Civil and Building Works |
Main Station Building, 275kV Switching Station Building, Shunt
Reactor, Chimney, Drainage
& Road,
Fire Services Water Tank and Fire
Pump House, C.W. Culvert System &
Equipment Room, C.W. Pump Equipment Room, Gas Receiving Station, Pipe & Cable
Rack and Lamma Power Station Addition and Alteration (LPS A&A) Works |
|
Unit L9 Mechanical Erection |
Erection of HRSG, Steam Turbine, Gas Turbine, Generator,
Condenser, Aux Equipment, Air duct / Inlet Filter, HRSG Inlet Duct
and Piping Support / Piping Erection; Insulation Work; and Installation of
Platform, Pipe Rack, Intake Aux Equipment, Bop piping and GRS piping |
|
Unit L9 Electrical, Instrumentation & Control
Erection |
Cable
Tray Cover Installation, Instrument Piping Installation and Cable Termination
|
|
Transmission System |
Backfilling
above portal structure for Cable
Duct 2 and cable trench from N4 landing point to Cable Duct no.2 Entrance |
|
Miscellaneous |
Slurry ash
piping & filling |
Environmental
Monitoring Works
All monitoring work at designated stations was performed
as scheduled satisfactorily.
Air Quality
No exceedance of Action/Limit levels on 1-hour TSP and 24-hour TSP for air quality was recorded in the month.
Noise
Construction work for Lamma Extension was carried out during the restricted hours including evening-time, holidays and night-time under valid Construction
Noise Permits. No exceedance of Action
and Limit levels
for noise arising from the construction of Lamma
Extension and transmission system was recorded in the month.
Site Environmental Audit
Independent Environmental
Checker (IEC) conducted a site inspection on 19/07/2006. The inspection result is
attached in Appendix H.
Site audits
were carried out on a weekly basis to monitor environmental issues on the construction site. The site conditions were generally
satisfactory. All required mitigation
measures were implemented.
Environmental Licensing and Permitting
|
Description |
Permit No. |
Valid Period |
Issued To |
Date of Issuance |
|
|
From |
To |
||||
|
Varied Environmental
Permit |
EP-071/2000/C |
18/05/05 |
- |
HEC |
18/05/05 |
|
Construction Noise
Permit |
GW-RS0032-06 |
11/02/06 |
10/08/06 |
Contractor |
27/01/06 |
|
Construction Noise
Permit |
GW-RS0138-06 |
24/03/06 |
21/09/06 |
Contractor |
24/03/06 |
|
Construction Noise
Permit |
GW-RS0278-06 |
24/05/06 |
19/11/06 |
Contractor |
24/05/06 |
|
Registration
of Chemical Waste Producer |
WPN5213-912-P2781-07 |
11/06/04 |
- |
Contractor |
11/06/04 |
|
Registration
of Chemical Waste Producer |
WPN5213-912-K2801-03 |
15/09/04 |
- |
Contractor |
15/09/04 |
|
Registration
of Chemical Waste Producer |
WPN5517-912-T2007-02 |
17/03/05 |
- |
Contractor |
17/03/05 |
|
Registration
of Chemical Waste Producer |
WPN5213-912-W2852-09 |
25/01/05 |
- |
Contractor |
25/01/05 |
|
Registration
of Chemical Waste Producer |
WPN4111-912-M2534-09 |
20/06/05 |
- |
Contractor |
20/06/05 |
|
WPCO
Discharge Licence |
EP890/W2/XD020 |
22/11/04 |
30/11/09 |
Contractor |
22/11/04 |
|
WPCO
Discharge Licence |
EP890/W2/XD021 |
03/02/05 |
28/02/10 |
Contractor |
03/02/05 |
|
WPCO
Discharge Licence |
EP890/W2/XD008
(V.1) |
29/06/06 |
30/11/09 |
HEC |
29/06/06 |
|
APCO Specified Process Licence |
L-7-028 |
22/06/06 |
31/12/08 |
HEC |
22/06/06 |
Implementation
Status of Environmental Mitigation Measures
Environmental
mitigation measures for the construction activities
as recommended
in the EM&A manual were implemented in the reporting month.
Environmental
Complaints
No complaint against the
construction activities was received in the reporting month.
Future Key
Issues
The future key issues to be
considered in the coming month are as follows:
Unit L9 Civil and Building
Works
-
to continue monitoring
the noise level during construction and to ensure compliance with the
CNP’s already obtained;
-
to continue executing the preventive
measures for avoiding noise exceedance and keep monitoring/ reviewing the
performance;
-
to monitor and
review the sufficiency of the dust suppression measures provided and increase
the resources accordingly if necessary;
Unit L9 Mechanical Erection
-
to continue monitoring
the noise level during construction
-
to continue executing the preventive
measures for avoiding noise exceedance and keep monitoring/ reviewing the
performance;
-
to monitor and
review the sufficiency of the dust suppression measures provided and increase
the resources accordingly if necessary;
Unit L9 Electrical Erection
-
to continue monitoring
the noise level during construction
-
to continue executing the preventive
measures for avoiding noise exceedance and keep monitoring/ reviewing the
performance;
-
to monitor and
review the sufficiency of the dust suppression measures provided and increase
the resources accordingly if necessary;
Transmission System
-
to continue monitoring
the noise level during construction;
-
to continue executing
the preventive measures for avoiding noise exceedance and keep monitoring/
reviewing the performance;
-
to monitor and
review the sufficiency of the dust suppression measures provided and increase
the resources accordingly if necessary;
-
to closely monitor the
construction activities in order to avoid disturbance to the rare plants;
-
to provide temporary
fire fighting equipment for prevention of fire within the work sites.
Concluding
Remarks
The environmental performance of the project was
generally satisfactory.
The Environmental Team (hereinafter called the “ET”) was formed within the Hongkong Electric Co. Ltd (HEC) to undertake Environmental Monitoring and Audit for “Construction of Lamma Power Station Extension” (hereinafter called the “Project”). Under the requirements of Section 6 of Environmental Permit EP-071/2000/C, an EM&A programme for impact environmental monitoring set out in the EM&A Manual (Construction Phase) is required to be implemented. In accordance with the EM&A Manual, environmental monitoring of air quality, noise and water quality and regular environmental audits are required for the Project. As the post-project marine water monitoring was successfully completed in September 2002, no further water quality monitoring for the reclamation works would be required.
The
Project involves the construction of a gas-fired power station employing
combined cycled gas turbine technology, forming an extension to the existing
Lamma Power Station. The key elements of
the Project including the construction activities associated with the
transmission system and submarine gas pipeline are outlined as follows.
· dredging and reclamation to form approximately 22 hectares of usable area;
· construction of six 300MW class gas-fired combined cycle units;
· construction of a gas receiving station;
·
construction of a new
transmission system linking the Lamma Extension to load centres on
· laying of a gas pipeline for the supply of natural gas to the new power station
This report summarizes the environmental
monitoring and audit work for the Project for the month of July 2006.
An Environmental Management
Committee (EMC) has been set up in HEC to oversee the Project. The management structure includes the following:
· Environmental Protection Department (The Authority);
· Environmental Manager (The Chairman of the Environmental Management Committee);
· Engineer;
· Independent Environmental Checker (IEC);
· Environmental Team (ET);
· Contractor.
The project organisation chart for the construction EM&A programme is shown in Appendix A.
1.3
Construction Works undertaken
during the Reporting Month
Construction activities for Unit L9 civil and
building works were for the
The main construction activities carried out during the reporting month and the corresponding environmental mitigation measures are summarized in Table 1.1. The implementation of major mitigation measures in the month is provided in Appendix I.
Table 1.1 Construction Activities and Their Corresponding Environmental Mitigation Measures
|
Item |
Construction Activities |
Environmental Mitigation Measures |
|
Unit L9 Civil and Building Works |
||
|
1 |
|
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and
implemented. |
|
2 |
275kV
Switching |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted and
implemented. |
|
3 |
Shunt
Reactor |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
4 |
Chimney |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
5 |
Drainage
& Road Works |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
6 |
Fire Services Water Tank and Fire Pump House |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
7 |
C.W.
Culvert System & Equipment Room |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
8 |
C.W. Pump Equipment Room |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
9 |
Gas Receiving Station |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
10 |
Pipe
& Cable Rack |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
11 |
LPS
A&A Works |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
Construction
of Transmission System
|
||
|
12 |
Backfilling above portal structure for Cable Duct 2 and cable trench from N4 landing point to Cable Duct no.2 Entrance |
Terrestrial Ecology
- Special care and close monitoring to avoid disturbances to the rare plant species. -
Temporary fire fighting
equipment provided within the work area during construction. |
|
13 |
Backfilling & Cable Protection |
Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. |
Unit
L9 Mechanical Erection
|
||
|
14 |
HRSG
Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
15 |
Steam
Turbine Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
16 |
Gas Turbine
Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan submitted
and implemented. |
|
17 |
Generator
Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
18 |
Condenser
Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
19 |
Auxiliary
Equipment Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
20 |
Air duct /
Inlet Filter |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
21 |
HRSG Inlet
Duct |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
22 |
Piping Support
/ Piping Erection |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
23 |
Insulation
Work |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
24 |
Platform
Installation |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
25 |
Pipe Rack
Installation |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
26 |
Intake Aux Equipment
Installation |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
27 |
Bop piping
installation |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
28 |
GRS piping
installation |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
Unit
L9 Electrical, Instrumentation & Control Erection
|
||
|
29 |
Cable Tray Cover Installation |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
30 |
Instrument
Piping Installation |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
|
31 |
Cable Termination |
Air
-
Dust suppression measures
implemented. Noise
-
General noise mitigation
measures employed at all work sites throughout the construction phase. Waste
Management -
Waste Management Plan
submitted and implemented. |
Miscellaneous |
||
|
32 |
Slurry
ash piping & filling |
Noise
- General noise mitigation measures implemented and silent type equipment deployed. |
1.4 Summary of EM&A Requirements
The EM&A program requires environmental monitoring for air,
noise and water
quality. As the post-project marine water monitoring was successfully
completed in September 2002, no further water quality monitoring for the
reclamation works would be required. The detailed EM&A monitoring work for air quality and noise are described in Sections 2 and 3
respectively. Regular environmental site audits for air quality, noise, water quality and waste management were carried out.
The following environmental
audits are summarized in Section 4 of this report:
· Environmental monitoring results;
· Waste Management Records;
· Weekly site audit results;
· The status of environmental licensing and permits for the Project;
· The implementation status of environmental protection and pollution control/ mitigation measures.
Future key issues will be reported in Section 5 of this report.
1-hour and 24-hour TSP monitoring at agreed frequencies were conducted to monitor air
quality. The impact
monitoring data were checked against the Action/Limit Levels as determined in the Baseline Monitoring
Report (Construction Phase). Appendix B
shows the established Action/Limit Levels for Air Quality.
Three
dust monitoring locations were selected for 1-hour TSP sampling (AM1, AM2 &
AM3) while four monitoring locations were selected for 24-hour TSP sampling
(AM1, AM2, AM3 and AM4). Table
2.1 tabulates the monitoring stations.
The locations of the monitoring stations are shown in Figure
2.1.
Table 2.1 Air Quality Monitoring Locations
|
Location I.D. |
Description |
|
AM1 |
Reservoir |
|
AM2 |
East Gate |
|
AM3 |
Ash Lagoon |
|
AM4 |
|
Continuous
24-hour TSP air quality monitoring was performed using the GS2310 High Volume
Air Samplers (HVAS), Partisol Model 2000 Sampler and the MINIVOL Portable
Sampler at AM1&2, AM3 and AM4 respectively.
TEOM Model 1400a continuous dust monitors were used to carry out 1-hour
TSP monitoring at AM1, AM2 and AM3. Table 2.2 summarises the equipment used in dust monitoring.
Table 2.2 Air Quality Monitoring Equipment
|
Equipment |
Model and Make |
|
24-hour
sampling: HVAS
Sampler Partisol
Air Sampler MINIVOL
Portable Sampler 1-hour
sampling: Continuous
TSP Dust Meter |
Model GS2310 Anderson Instruments Inc. Partisol Model 2000 Rupprecht & Patashnick AIRMETRICS TEOM Model 1400a Rupprecht & Patashnick |
2.4
Monitoring
Parameters, Frequency and Duration
Table 2.3 summarises the monitoring parameters, duration and
frequency of air quality monitoring. The
monitoring schedule for the reporting month is shown in Appendix
C.
Table 2.3 Air Quality Monitoring Parameter,
Duration and Frequency
|
Monitoring Stations |
Parameter |
Duration |
Frequency |
|
AM1 |
1-hour TSP |
1 |
3 hourly samples every 6
days |
|
24-hour TSP |
24 |
Once every 6 days |
|
|
AM2 |
1-hour TSP |
1 |
3 hourly samples every 6
days |
|
24-hour TSP |
24 |
Once every 6 days |
|
|
AM3 |
1-hour TSP |
1 |
3 hourly samples every 6
days |
|
24-hour TSP |
24 |
Once every 6 days |
|
|
AM4 |
24-hour TSP |
24 |
Once every 6 days |
2.5
Monitoring Procedures and Calibration Details
24- hour TSP Monitor:
Preparation of
Filter Papers
· Visual inspection of filter papers was carried out to ensure that there were no pinholes, tears and creases;
· The filter papers were then labeled before sampling.
· The filter papers were equilibrated at room temperature and relative humidity < 50% for at least 24 hours before weighing.
Field Monitoring
· During collection of the sampled filter paper, the information on the elapse timer was logged. Site observations around the monitoring stations, which might have affected the monitoring results, were also recorded. Major pollution sources, if any, would be identified and reported. The flow record chart for the previous sampling was checked to see if there was any abnormality.
· The post-sampling filter papers were removed carefully from the filter holder and folded to avoid loss of fibres or dust particles from the filter papers;
· The filter holder and its surrounding were cleaned;
· A pre-weighed blank filter paper for the next sampling was put in place and aligned carefully. The filter holder was then tightened firmly to avoid leakage;
· A new flow record chart was loaded into the flow recorder;
· The programmable timer was set for the next 24 hrs sampling period, ±1/2 hr;
· The post-sampling filter papers were equilibrated at room temperature and relative humidity < 50% for at least 24 hours before weighing.
1- hour TSP Monitor:
· The following parameters of the TEOM model dust meters are regularly checked to ensure proper functionality:
o Mass concentration;
o Total mass;
o Frequency of the tapered element;
o Electrical noise;
o Main flow;
o Auxiliary flow.
Maintenance
& Calibration
· The monitoring equipment and their accessories are maintained in good working conditions.
· Monitoring equipment is calibrated at monthly intervals. Calibration details are shown in Appendix F.
All dust monitoring works were conducted on schedule. All monitoring data and graphical
presentation of the monitoring results are provided in Appendix
D. Key findings and observations are
provided below:
1-hour TSP
No
exceedance of 1-hour TSP Action/Limit Level was recorded in the month.
24-hour TSP
No exceedance of 24-hour TSP Action/Limit Level
was recorded in the month.
Continuous noise alarm monitoring at Ash Lagoon/Ching Lam were carried out to calculate the noise contributed by the construction activities at the two critical NSR’s, viz. Long Tsai Tsuen/Hung Shing Ye and the school within the village of Tai Wan San Tsuen. The impact monitoring data for construction noise were checked against the limit levels specified in the EM&A Manual. With the availability of the construction noise permits, impact monitoring for the construction work during the restricted hours was also carried out. Section 4 presents the details of the construction noise permits.
Manual noise measurements at Pak Kok Tsui residences
were carried out for the construction work of Transmission System in this reporting month. The impact noise monitoring
data were checked against the limit levels specified in
the EM&A Manual. Appendix B shows the established Action/Limit Levels
for noise.
In accordance with the EM&A manual, the identified noise monitoring locations are listed in Table 3.1 and shown in Figure 3.1 and Figure 3.2.
Table 3.1 Noise Monitoring Locations
|
Purpose of noise monitoring |
Monitoring Location |
|
Lamma Extension |
Ash Lagoon |
|
Lamma Extension |
Ching Lam |
|
Transmission System |
Pak Kok Tsui residences (No.2 and No.8) |
The sound level meters used for noise monitoring complied with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1). The noise monitoring equipment used is shown in Table 3.2.